Specifications & Guidelines for Safe Concrete Pumping Operations

Views :
Update time : 2025-11-09
Safe pumping starts with numbers. Zoom GlobalMech Corp mandates that operators calculate Maximum Theoretical Pressure (MTP) before every pour: MTP = (Line length × Friction factor) + (Vertical height × 0.22 bar/m) + (Bend equivalent length × 0.5 bar). If MTP exceeds 85 % of pump rated pressure, reduce line diameter or stage the pour. Keep a laminated chart inside the cab; guessing kills pipelines—and people.



Pipeline specification: use 125 mm OD pipe for outputs above 80 m³/h; 100 mm is acceptable below that, but velocity must stay under 5 m/s to prevent segregation. Always place a 1 m long 150-to-125 mm tapered reducer at the hopper outlet to minimize turbulence. Gaskets are rated for 150 bar; discard any with visible cracks or Shore-A hardness below 70. Secure every coupling with two safety pins at 90 ° apart; vibration loosens single pins within 20 minutes of high-pressure pumping.

 


 
Personnel: establish a 10 m exclusion zone around the end-hose; a whipping 5-inch hose generates 3 500 N of force—enough to fracture bones. Equip the nozzleman with a dead-man remote that defaults to STOP when released. Finally, test emergency stop buttons monthly; 17 % of injuries occur when E-sticks fail due to concrete splash seizing the switch.
Related News
Read More >>
Specifications & Guideline Specifications & Guideline
11 .09.2025
Specifications & Guidelines for Safe Concrete Pumping Operations
How to Pump Concrete: From Mix How to Pump Concrete: From Mix
11 .09.2025
How to Pump Concrete: From Mix Design to Final Placement
Why Concrete Pumps Clog: Root Why Concrete Pumps Clog: Root
11 .08.2025
Why Concrete Pumps Clog: Root Causes & Field Solutions
Step-by-Step Debug Guide for T Step-by-Step Debug Guide for T
11 .08.2025
Step-by-Step Debug Guide for Trailer-Mounted Mixer Pumps

Leave Your Message